How is on-site installation and commissioning arranged?

The standard flow is: confirm site conditions before arrival (power, earthing, table levelness, ambient temperature, humidity and vibration); our engineers then arrive for unboxing inspection, mechanical installation, electrical wiring, accuracy calibration and program commissioning; validate with your own parts against the acceptance criteria; and on passing, run operator and maintenance training and sign the acceptance record. The whole process usually takes several days depending on equipment complexity and integration workload. If you need the work scheduled around holidays or production peaks, book it in advance.